Supreme Court: Mere Allegation of Contractual Breach Insufficient for Blacklisting

Contractual Breach

In M/S Techno Prints v. Chhattisgarh Textbook Corporation & Anr. (2025 INSC 236), the Supreme Court of India ruled that a contractor cannot be blacklisted solely based on allegations of contractual breach unless there is a clear intent to cheat or take undue advantage. The decision reinforces that blacklisting, being a severe penalty, must be based on substantive grounds rather than mere non-performance due to unforeseen circumstances.

Facts of the Case

The appellant, M/S Techno Prints, was awarded a contract for printing textbooks by the Chhattisgarh Textbook Corporation. The contract stipulated specific timelines for completion. However, due to the COVID-19 pandemic, the appellant failed to meet the deadline. Subsequently, the Corporation issued a show cause notice, citing breach of contract and proposing blacklisting the appellant for three years while forfeiting the Earnest Money Deposit (EMD).

The appellant challenged the notice before the High Court, arguing that the delay was beyond its control. The High Court dismissed the writ petition, affirming the Corporation’s authority to blacklist defaulting contractors under the tender conditions. Dissatisfied with the ruling, the appellant approached the Supreme Court.

Key Legal Issues

  1. Whether a mere breach of contract justifies blacklisting a contractor.
  2. Whether procedural fairness was followed in issuing the show cause notice.
  3. Whether the Corporation’s actions were arbitrary or violated principles of natural justice.

Arguments by the Parties

Appellant (M/S Techno Prints):

  • The delay was due to the COVID-19 pandemic, an unforeseeable event beyond its control.
  • Blacklisting is an extreme punitive measure, appropriate only in cases of fraud, willful misconduct, or habitual default.
  • The Corporation arbitrarily refused to consider the genuine constraints caused by the pandemic.

Respondent (Chhattisgarh Textbook Corporation):

  • The contract clearly stipulated penalties, including blacklisting, for failure to meet deadlines.
  • The delay caused significant financial and operational losses to the Corporation.
  • The show cause notice provided the appellant an opportunity to explain its failure.

Supreme Court’s Reasoning

1. Breach of Contract vs. Blacklisting

The Court distinguished between a mere breach of contract and conduct warranting blacklisting. Citing Kulja Industries Ltd. v. BSNL (2014) AIR SC 9, it reiterated that blacklisting must be justified by habitual failure, fraud, or gross negligence. The Court emphasized that:

  • Blacklisting is a severe penalty with long-term consequences on a business’s reputation and ability to secure future contracts.
  • It cannot be imposed merely because a contractor fails to perform due to external factors.
  • The Corporation’s actions were disproportionate given the pandemic’s widespread impact.

2. Procedural Fairness and Natural Justice

The Court found that the show cause notice failed to provide specific reasons justifying blacklisting. Referring to Erusian Equipment & Chemicals Ltd. v. State of West Bengal (1975) 1 SCC 70, it reaffirmed that blacklisting must be based on strong and independent evidence of misconduct. The notice lacked sufficient details to establish willful default or bad faith.

3. Case Law Considerations

The Court relied on The Blue Dreamz Advertising Pvt. Ltd. v. Kolkata Municipal Corporation (2024 INSC 589), where it held that:

  • Blacklisting should only be imposed when necessary to protect public interest from irresponsible contractors.
  • If a dispute arises purely from contractual performance issues, standard remedies like forfeiture of security deposits should be pursued instead of blacklisting.

Conclusion and Implications

The Supreme Court quashed the blacklisting notice but upheld the Corporation’s right to forfeit the EMD. It emphasized that while contractual obligations must be enforced, blacklisting is a punitive measure that requires a higher threshold of misconduct.

This ruling reinforces the principle that blacklisting cannot be an automatic consequence of non-performance. Contractors facing similar actions must ensure that the grounds for blacklisting meet legal scrutiny. Public authorities must exercise discretion, ensuring that blacklisting is reserved for cases of fraud, habitual default, or gross negligence rather than routine contract disputes.

FAQs:

1. Can a contractor be blacklisted for failing to perform a contract due to unforeseen circumstances like COVID-19?

No, the Supreme Court ruled that mere non-performance due to uncontrollable external events—such as the COVID-19 pandemic—does not justify blacklisting. In M/S Techno Prints v. Chhattisgarh Textbook Corporation, the Court held that blacklisting is a punitive measure and should be reserved for cases involving fraud, habitual default, or willful misconduct, not standard contractual breaches.

2. What are the legal requirements before a contractor can be blacklisted by a government authority?

The authority must follow the principles of natural justice, which includes:

  • Issuing a detailed show cause notice specifying the reasons for blacklisting,

  • Providing the contractor an opportunity to respond,

  • Basing the decision on concrete evidence of misconduct, not mere allegations.

The Supreme Court emphasized in this case that blacklisting must be proportionate, reasoned, and not arbitrary.

3. Is blacklisting a proportionate response to a one-time delay in contract performance?

No, according to the Supreme Court, blacklisting for a one-time delay—particularly when caused by external factors like a pandemic—is disproportionate and unreasonable. The Court stated that blacklisting affects a contractor’s livelihood and business reputation and thus should only be used in serious cases involving malafide conduct.

4. What alternative remedies are available to public authorities in cases of delayed or failed contract execution?

Instead of blacklisting, public bodies can:

  • Forfeit the Earnest Money Deposit (EMD) or security deposit,

  • Impose liquidated damages as per the contract terms,

  • Terminate the contract for breach of terms.

The Court in Techno Prints clarified that routine contractual disputes must be resolved using contractual remedies, not punitive blacklisting unless there’s clear evidence of deceit or fraud.

5. What precedent does the Techno Prints judgment set for future government contracting disputes?

The 2025 judgment strengthens legal protections for contractors by:

  • Reaffirming that blacklisting cannot be automatic,

  • Ensuring that contractual non-performance is treated differently from misconduct,

  • Requiring strict adherence to procedural fairness before imposing severe sanctions.

This decision will likely prevent arbitrary blacklisting by public authorities and ensure that contractors are not unfairly penalized for genuine delays.

Stay informed with insights that matter. Follow us for more updates on key legal developments.

Disclaimer

The content provided here is for general information only; it does not constitute legal advice. Reading them does not create a lawyer-client relationship, and Mahendra Bhavsar & Co. disclaims all liability for actions taken or omitted based on this content. Always obtain advice from qualified counsel for your specific circumstances. © Mahendra Bhavsar & Co.

author avatar
Mahendra Bhavsar & Co.